Item Coversheet
CITY OF PEORIA, ARIZONA
COUNCIL COMMUNICATION
 
Agenda Item: 6C. 


Date Prepared:  3/6/2024 Council Meeting Date: 4/16/2024

TO:Mike Faust, City Manager 
THROUGH:
Mike Faust, Deputy City Manager 
FROM:  Dan Nissen, P.E., Acting Development and Engineering Director 
SUBJECT:
Intergovernmental Agreement Amendment, State of Arizona and Budget Amendment, Stadium Trail Phase 2, 75th Avenue to Skunk Creek 

Purpose:

Discussion and possible action to adopt RES. 2024-23 approving Amendment No. One to the Intergovernmental Agreement with the State of Arizona and approve a budget amendment in the amount of $12,000 from contingency for the local cost share, design, construction, and construction management of Stadium Trail Phase 2, a multi-use trail located along 75th Avenue to Skunk Creek. 

Summary:

In 2018, the City applied for and received federal funding for the construction of a new multi-use pathway known as Stadium Trail, located along the north side of Skunk Creek from 83rd Avenue to 73rd Avenue. Stadium Trail consists of a multi-use concrete path with unpaved shoulders and is situated primarily within land currently owned by the City of Peoria and the Flood Control District of Maricopa County (FCDMC). Phase 1 is under construction and anticipate completion later this year. The Stadium Trail Phase 2 project will build on the improvements constructed with Phase 1 and consists of approximately 0.15 miles of new multi-use path, a clear span pedestrian bridge of Skunk Creek upstream of its confluence with the ACDC, and an undercrossing of the 75th Avenue bridge to connect to the existing trail along the ACDC east of 75th Avenue.

 

In order to receive federal funding and comply with federal design, land acquisition and construction processes, the City entered into an Intergovernmental Agreement (IGA) with the State (Arizona Department of Transportation).  The IGA included both federal and local City funds to pay for the design and construction of the project, which at that time was estimated to be $2,703,608.00. Of that amount, $260,000.00 was budgeted for design and $2,443,608.00 for construction. The City’s share of the original estimated amount was $399,286.   

 

As the design moved forward, the estimated cost of construction increased to $4,182,255.00. To address and mitigate the cost increase, staff worked with Maricopa Association of Governments (MAG) and applied for close-out funding. This effort was successful, and MAG awarded the City an additional $1,639,544.00 in federal funding resulting in the City receiving a total of $3,943,866.00 in federal aid for construction. The City’s contribution for construction also increased similarly from $139,286.00 to $238,389.00. The purpose of Amendment No. One to the IGA is to revise the design and construction costs in the Agreement to correspond to the additional federal construction funding and the corresponding increase in City construction funding.  The estimated federal and local costs for design and construction are summarized in the Project Cost Summary Table.

 

PROJECT COST SUMMARY TABLE

 

DESIGN AND ADMINISTRATIVE COSTS*

·         Design ....................................................................................... $    479,593.57

·         Administrative Costs (ADOT)....................................................  $      30,000.00

·         Total Design and Administrative Cost........................................  $    509,593.57

ESTIMATED CONSTRUCTION COSTS

·         Federal Construction Funding.................................................... $3,943,866.00

·         Local Construction Funding........................................................ $   238,389.00

·         Total Estimated Construction Cost.............................................. $4,182,255.00

* All design and administrative costs are locally funded and born by the City.

 

Staff had initially anticipated execution of this agreement in FY25 and have requested funding to accommodate the increased local match in FY25 CIP. However, in order to meet the current schedule for obligation of Federal funding and associated administrative processes, ADOT has initiated this modification this fiscal year, necessitating the request for additional funding from contingency.

 

The design for the project is complete. Construction is anticipated to begin in the fall of 2024 and be complete by fall 2025.


 

Previous Actions/Background:

  • June 2016 - Applied for MAG Design Assistance Funding for Project Assessment
  • July 2017 - Completed the Project Assessment
  • Spring 2018 - Regional Federal Funding for Construction
  • November 2021 City Council approval of IGA with ADOT for Design and Construction
Staff Recommendation:

Staff recommends adoption of RES. 2024-23 approving Amendment No. One to the Intergovernmental Agreement with the State of Arizona and approval of a budget amendment in the amount of $12,000 from contingency for the local cost share, design, construction, and construction management for Stadium Trail Phase 2.

Fiscal Analysis:

Funding for this project is available in the FY2024-FY2033 Capital Improvement Program in the Stadium Trail Phase 2 project budget. Payments for the City cost share will be made from 4254-4254-543011-CIPPK-CS00232.
ATTACHMENTS:
Description
Exhibit 1: Resolution
Exhibit 2: Vicinity Map
Exhibit 3: Location Map
Exhibit 4: IGA
Contact Name and Number:  
Dan Nissen, PE, (623) 773-7214